Who pays when existing infrastructure has to move for a project.
Esshaki Legal Media TeamCurrent as of October 2026
Development frequently requires relocating existing utility facilities, and the
cost allocation depends on the nature of the utility’s right.
Facilities in a public right-of-way are generally there under a franchise or
statutory authority, subject to the public authority’s right to require
relocation for a public purpose at the utility’s expense. Relocation for a
private development is usually at the developer’s expense.
Facilities under a private easement may not be relocated without the
utility’s consent, and the utility can demand payment or refuse. The terms of the
easement govern, and a blanket easement gives the utility considerable
leverage.
Timing. Utility relocation is the most common cause of construction delay,
and utilities operate on their own schedules. Relocation agreements should be in
place before the construction schedule is fixed, with commitments on timing.
Design coordination. Conflicts identified by subsurface investigation rather
than by discovery during excavation, which is far more expensive.
Damage to facilities. Statutory notification systems require locate requests
before excavation, with penalties and liability for damage caused by failure to
request or to respect the marks.
New easements. Utilities require easements for new facilities, and their
standard forms are broader than necessary. Negotiating location, width and
permitted uses is worthwhile.