Sequencing approvals so that the schedule is real.
Esshaki Legal Media TeamCurrent as of May 2025
Development schedules fail because approvals are sequenced optimistically. A
disciplined process makes the timeline credible.
Map the approvals. Every federal, state, county and local approval, with the
issuing body, the meeting calendar, the statutory decision period, the
application requirements and the appeal window.
Identify dependencies. Which approvals require another first — a wetlands
determination before site plan, a plat before building permits, a driveway
permit from the road authority before site plan approval.
Meeting calendars. Local bodies meet monthly, and a missed submission
deadline costs a full cycle. Build the schedule to the calendar rather than to
the review period.
Completeness. Incomplete applications restart the clock. Confirm the
checklist with staff and submit complete.
Appeal periods. An approval is not final until the appeal window closes.
Financing and construction commitments should account for it.
Pre-application engagement with staff and with neighbors, which is the
single most effective way to shorten the discretionary approvals.
Parallel processing where permitted — submitting building plans while
zoning approval is pending, at risk.
Contingency. One full cycle of slack in the schedule, because something will
be continued.