Zoning may change while a project is in progress. Whether the earlier rules continue to govern depends on the state’s vesting doctrine.

Common law vesting generally requires a lawfully issued permit plus substantial expenditure or construction in good faith reliance on it. Planning costs, engineering fees and land acquisition often do not suffice; physical commencement usually does.

Statutory vesting in many states fixes rights on the filing of a complete application, the approval of a preliminary plat, or the issuance of a building permit, for a defined period.

Pending ordinance doctrine. Some jurisdictions permit denial of an application filed after a zoning amendment has been formally initiated, which makes the timing of filing critical.

Moratoria. A temporary halt on approvals while a plan is studied is generally permitted if reasonable in duration and scope and adopted for a legitimate planning purpose. Indefinite moratoria invite takings claims.

Development agreements are the reliable answer where the state authorizes them, fixing the applicable rules by contract for a stated term.

Practical sequencing for developers. Obtain the discretionary approvals first, secure a permit, commence physical work of a substantial nature, and document expenditures contemporaneously with dates and amounts. Vesting disputes are decided on that record.